Downtown Project

DOWNTOWN PROJECT CONSTRUCTION UPDATE

Updates for the Downtown Construction Project

Phase 1B - 2nd Street and Lenora Street – Traffic control was taken down and Lenora Street and 2nd Street are both now open to two-way traffic. Construction crews will continue to work on paver installation and clean-up in isolated areas downtown for the next couple of weeks. 

Phase 2A – Park Street and Veteran’s Alley – Veteran’s Alley will remain closed from 1st Street to 2nd Street through next week. Paving crews will be working to install asphalt 11/23 on a few remaining items in front of the Library, City Hall, and other businesses on the south side of Park Street and near the 1st & Park Street intersection. Veteran’s Alley is anticipated to be paved the in December and will be re-opened to normal traffic after asphalt is installed.

Phase 2BPark Street and Veteran’s Alley – Surface Improvements construction contract.  The project consists of surface utility, drainage, sidewalk and streetscape, roadway section, paving and signage and striping improvements.  The project also includes a bid alternate for the work and costs related to constructing the City Campus’s new driveway to be located just west of City Hall in coordination with and as part of the approved development agreement and approved plans the Treasure Valley Transit Center.  The new driveway will replace the current driveway located between City Hall and the McCall Library

Summer 2020 Road Closures:

  • Granite Construction will  be closing the intersection of 2nd and Park Street - it is anticipated this will remain closed until mid-July.
  • Park Street between 2nd Street and 1st Street, including the intersection of 2nd and Park Street will be fully closed and it is anticipated that it will remain closed until mid-July.
  • During the closure of Park Street between 2nd and 1st Street access to the Library, Washington Federal Bank, and City Hall will only be accessible from 1st Street by way of the Senior Center/Central District Health Dept. parking lot.

*Schedule subject to change

Downtown Core Project Logo

Drawing9(1).jpg

WHY REVITALIZE DOWNTOWN?

The “Heart” of our City is McCall’s Downtown. Its the gathering place for the community and a sense of arrival for visitors. The first glimpse of Payette Lake when entering Downtown McCall leaves a lasting impression on anyone who has visited. The Downtown Project aims to increase the energy of the area and create a vibrant and attractive destination for both residents and visitors. This project will transform our  Downtown into a symbol of pride for the community and establish McCall’s identity. Restoring McCall’s Downtown is an important economic catalyst for attracting new businesses, residents, and visitors to McCall.

The current dilapidated condition of Downtown McCall roads display the need to rebuild. The Streets L.O.T. has provided a financial solution to repair an important reflection of McCall’s overall character. City of McCall remains focused on maintaining and improving the physical and economic aspects of Downtown McCall for visitors, residents and the business community.

Damaged Street Picture

Damaged Corner Lenora Street Picture

Damaged Street Lenora
Park Street / 2nd Street
Looking West
2nd Street
on the NW Corner of Lenora
2nd Street Looking North
in front of Albertson's Market


2nd Street Existing       2nd Street Proposed

OVERVIEW Logo(1).jpg

Over the next four years McCall’s Downtown will get a complete facelift. Over the course of shorter construction phases, crews will aim to keep impacts to a minimum and utilize our short summer construction window.Downtown Improvements.png

2nd Street
The center of downtown and therefore calls for a unique design. Including special pavement treatments and rolled curbs will create an area for public gathering events.

Lenora, Park & 1st  Street*
These typical streets with low speeds, short blocks, and relatively low traffic volumes provide important pedestrian connections to the Downtown, parking and the Lakefront.

Veteran’s Alley
This important utility corridor will see overhead utility lines converted to underground as well as water, sewer and stormwater improvements. The alley will also be paved 100%.

*May take additional time to complete based on funding sources.


4 to 5 Years of construction time will include:

  • New roadway surfaces
  • Improved sidewalks
  • Streetscaping
  • On-street parking
  • Enhanced pedestrian intersections
  • Utility upgrades*
  • Event spaces*
  • Outside seating**
  • Street lighting
  • Storm water upgrades
  • Integrated public artwork**
*Funded by sources other than the Streets  Local Option Tax (Streets L.O.T.)
*May take additional time to complete based on funding sources.
timelin5.png

Summer / Fall 2020

In the summer of 2020, construction continues in the downtown as the focus shifts to new roads and sidewalks. Closures will be conducted in stages to reduce impacts. Signs will be adequately posted to guide traffic. Pedestrian walkways will not always be accessible so look for alternate paths and signs to guide you. All businesses will remain open during their regular hours. 

Open for Business Graphic

Downtown Core Reconstruction Phase high.jpg

Getting Around Graphic

Sidewalk access will be open to all businesses and all businesses will be open according to their regular business hours. Signs will be posted to direct traffic.

Bus Transportation Treasure Valley Transit Red Line will be running offering free transport for those who need assistance getting around. Contact them at (208) 634-0003.
Find Parking

On-street parking will be limited due to road shut downs. Please use public lots that allow free multiple vehicle parking.


Fuding.jpg

Draw2AA0.pngThe Downtown Reconstruction Project uses Streets Local Option Tax dollars to restore streets.  These streets were allocated as a part of the McCall Improvement Plan as well as detailed for future growth in the Downtown Master Plan.

Underground infrastructure is being paid for by Streets Local Option Tax,  McCall Water Department, McCall Franchise Utility Fund, Payette Lakes Recreational Water and Sewer District, Idaho Power, Frontier Communications and Cable One.

Conceptual Drawing
View a conceptual draft of what the future of the Downtown in McCall could look like.


OUTREACH & PRESENTATIONS


OTHER DOCUMENTS


 


Project Leader
Nathan Stewart, Public Works Director
(208) 634-8943  Desk
(208) 315-3304  Cellular