McCall Public Library Expansion

The Library Expansion Project is officially under construction.  
WE ARE OPEN!

 The project to build a new, state-of-the-art library to serve the community for the next 50 years and beyond, expected to take two years, began with a ceremonial demolition of the old fire station. The building was removed to make room for the new structure that will front the existing library. Our team is now building the new library in front of the existing library and parking will be added on the east side. The new build will take 1½ years. Then, the existing library will be renovated. The entire project is scheduled to be completed by November 2024.


Thanks to our City of McCall Voters and generous donors the library is expanding.

What is included in the Library Expansion?

Renovation & repair of the 50-year-old building

Additional accessibility for all ages & mobility levels

Additional space to safely serve the public

Additional work, meeting, study & presentation spaces

Advancements in technology & access to equipment

Watch the original virtual Walkthrough video by clicking: here


Project Photo Gallery





Find frequently asked questions here: https://www.mccall.id.us/McCallLibraryExpansionFAQ



Construction Details
See Construction Images in our Gallery>

UPDATE

November 2023

November was a very productive month for our construction team at the McCall Library.  We have been pushing on getting the exterior cladding systems completed prior to winter, and we are getting close and only have the metal panels at the 2nd floor to complete at this point.  We will continue to push this install through the month of December so that we have everything done on the exterior and can focus on the interior finishes through the winter. On the inside of the building, we have started painting on the 1st floor, and are currently sheetrocking & taping on the 2nd floor.  Behind paint completion on the 1st floor, we will start installing tile, millwork, and mechanical / electrical / plumbing trim.  We are very happy with our progress, and are looking good to continue interior work through the winter and turn the addition over on time next spring.   

The latest project schedule from the City's contractor CM Company Shows: 

- Move-in date for the new addition: May 2024

- Move-in date for the renovated existing library: November 2024

ROAD & FACILITY ADVISORIES

New Entrance - NOW OPEN - SIGNS POSTS


 Open M-F 10-6, Saturdays 10-2.




Project Team:

Architect: 
Dennis Humphries, RATIO Architects
https://ratiodesign.com

Construction Manager: 
CM Company
www.cmcompany.com

On Site Contact:

Jimmie Miller

CM Company Project Superintendent

jimmie@cmcompany.com

208-371-5702


www.cmcompany.com

City of McCall Project Manager:

Nathan Stewart, Public Works Director

Public Outreach:

Media, Website, Library Patrons, Email, Text my gov, on-site signage - As needed 

Construction Impacts:

As Posted

Anticipated Project Schedule:

2022-2024