Warren Wagon Road Construction

Existing road conditions

Please be aware that the Federal Hwy Administration's Warren Wagon Road Project will begin July 9th., 2018 and is expected to be completed by November 1st, 2019. 

Contact Information

Project Engineer: John Henderson
Phone: 360-839-3867
Email: john.henderson@dot.gov

Federal Highway Administration
Western Federal Lands Highway Division
610 East Fifth Street
Vancouver, WA 98661
360-619-7700

  • The Contractor is allowed two 4-hour closures each workday Monday through Friday. Closure times are anticipated from 8:00 am to 12:00 pm; and afternoon closures occurring from 1:00 pm to 5:00 pm.
  • During open road periods delays up to 30 minutes may occur.
  • Two consecutive weeks of closures (Monday through Friday only) is allowed between September 4, 2018 and October 12, 2018.

Warren Wagon Rd is located along Payette Lake in McCall, ID in Valley county. The project starts at milepost 2.2 and completes at mile 5.7 at Eastside Drive. Work consists of excavation, grading, drainage, subgrade stabilization, AOP, base, paving, rock slope stabilization, and other small items of work. Work in 2018 will include culvert installations, rotomilling of existing asphalt, rock slope stabilization, and subgrade stabilization. Road base and paving will be completed in 2019.

For more information or contact on the project visit https://flh.fhwa.dot.gov/projects/id/warren-wagon/