McCall Public Library Expansion

The Library Expansion Project is officially under construction.  
WE ARE OPEN!

On Wednesday, August 17, the first milestone in new library construction was celebrated on the City Campus in front of the Library with a ceremonial event.

The project to build a new, state-of-the-art library to serve the community for the next 50 years and beyond, expected to take two years, began with a ceremonial demolition of the old fire station. The building is being removed to make room for the new structure that will front the existing library. After demolition is complete, a team will build the new library in front of the existing library and parking will be added on the east side. The new build will take 1½ years. Then, the existing library will be renovated. The entire project is scheduled to be completed by August 2024.


Thanks to our City of McCall Voters and generous donors the library is expanding.

What is included in the Library Expansion?

Renovation & repair of the 50-year-old building

Additional accessibility for all ages & mobility levels

Additional space to safely serve the public

Additional work, meeting, study & presentation spaces

Advancements in technology & access to equipment

Watch the original virtual Walkthrough video by clicking: here


Project Photo Gallery



Find frequently asked questions here: https://www.mccall.id.us/McCallLibraryExpansionFAQ



Construction Details
See Construction Images in our Gallery>

UPDATE

Spring 2023

  • With the great snow pack this year, our construction crew found ourselves in full snow removal mode upon remobilizing to the McCall Library site this early spring.  Once we were able to get the snow dealt with, we focused in on finishing up the foundations.  All exterior foundation walls are placed now, and we installed damp-proofing / water-proofing membrane and foundation insulation prior to backfill.  We placed all interior footings that will support the wood columns and beams last week, and we have started on underground mechanical / electrical / plumbing rough in.  This MEP rough in will continue for the next couple weeks, and we are shooting for a slab placement around June 20th.  Once the slab is placed, exterior wood framed walls will start, so we will see the building start to go vertical in June!

The latest project schedule from the City's contractor CM Company Shows: 

- Move in date for the new addition: May 2024

- Move in date for the renovated existing library: November 2024

ROAD & FACILITY ADVISORIES

New Entrance - NOW OPEN - SIGNS POSTS


 Open M-F 10-6, Saturdays 10-2.




Project Team:

Architect: 
Dennis Humphries, RATIO Architects
https://ratiodesign.com

Construction Manager: 
CM Company
www.cmcompany.com

On Site Contact:

Randy Gallentine 
CM Company Project Superintendent
randyg@cmcompany.com
 909-277-5784

www.cmcompany.com

City of McCall Project Manager:

Nathan Stewart, Public Works Director

Public Outreach:

Media, Website, Library Patrons, Email, Text my gov, on-site signage - As needed 

Construction Impacts:

As Posted

Anticipated Project Schedule:

2022-2024