McCall Public Library Expansion

The Library Expansion Project is officially under construction.  
WE ARE OPEN!

 The project to build a new, state-of-the-art library to serve the community for the next 50 years and beyond, expected to take two years, began with a ceremonial demolition of the old fire station. The building was removed to make room for the new structure that will front the existing library. Our team is now building the new library in front of the existing library and parking will be added on the east side. The new build will take 1½ years. Then, the existing library will be renovated. The entire project is scheduled to be completed by November 2024.


Thanks to our City of McCall Voters and generous donors the library is expanding.

What is included in the Library Expansion?

Renovation & repair of the 50-year-old building

Additional accessibility for all ages & mobility levels

Additional space to safely serve the public

Additional work, meeting, study & presentation spaces

Advancements in technology & access to equipment

Watch the original virtual Walkthrough video by clicking: here


Project Photo Gallery




Find frequently asked questions here: https://www.mccall.id.us/McCallLibraryExpansionFAQ



Construction Details
See Construction Images in our Gallery>

UPDATE

Summer 2023

  • The concrete slab for the library addition was placed on 6/20, and the wood framing started a few days later after the slab was properly cured.  Framing has been moving along very well, with the beautiful glue-lam columns and beams being set the 1st couple weeks of July, and the cross-laminated timber floor structure being installed the week of 7/17 – 7/21.  We have now started to frame the second-floor walls, and the glue-lam columns and beams for the 2nd floor will start installing next week and the roof structure will start to be installed in mid-August.  
     

The latest project schedule from the City's contractor CM Company Shows: 

- Move-in date for the new addition: May 2024

- Move-in date for the renovated existing library: November 2024

ROAD & FACILITY ADVISORIES

New Entrance - NOW OPEN - SIGNS POSTS


 Open M-F 10-6, Saturdays 10-2.




Project Team:

Architect: 
Dennis Humphries, RATIO Architects
https://ratiodesign.com

Construction Manager: 
CM Company
www.cmcompany.com

On Site Contact:

Jimmie Miller

CM Company Project Superintendent

jimmie@cmcompany.com

208-371-5702


www.cmcompany.com

City of McCall Project Manager:

Nathan Stewart, Public Works Director

Public Outreach:

Media, Website, Library Patrons, Email, Text my gov, on-site signage - As needed 

Construction Impacts:

As Posted

Anticipated Project Schedule:

2022-2024